BUILDING PERMIT
      Permit Number: 19-044
      Permit Date: 1/15/2019 11:59:14 AM


Project Information

Address:7036 NIEMAN RD

Add'l Addresses:
County Parcel ID:
Subdiv:

Project Name:

Family Tree Nursery Coffe Bar
Work Desc:

Add coffee bar
Value of Work:

$4000Occupancy Group:MType of Construction:V-BZoning:R1
Finished Area:




180Unfinished Basement/ Garage Area:Deck/Porch Size:Nbr Stories:1


Permit Requirements



Special Conditions:




Special Inspections Required?Automatic Sprinkler Required?Public Sidewalks?Number of Trees Required?




Applicant Information

Applicant of Record:Mike Cox Plumbing, Inc.
Address:42201 E State Rte. N
City, State ZIP:Creighton, MO 64739

* - You must obtain a Satisfactory Rough-In Inspection prior to concealing any components of the Structure, Electrical, Plumbing & Heating and Air conditioning installed on your project. A Rough-in Inspection is an inspection of all the above components.
Note: Each of the components, Structure, Electrical, Plumbing & Heating and Air Conditioning may be inspected individually and when all the completed have received a satisfactory inspection the Rough-In will be considered passed. See back of Permit Card for time frames for individual component inspections.

Call Codes Administration at least one day in advance at 913-742-6010 to schedule the inspection.


* - You must obtain a satisfactory Above Ceiling inspection before any portion of the finished ceiling is installed. All electrical, HVAC, plumbing and framing shall be complete and inspected simultaneously. Call Codes Administration at least four hours in advance at 913-742-6010 to schedule the inspection. Inspection requests must be received by 2 PM for a same day inspection.

* - The Final inspection is required before furnishings may be moved into the tenant space. A Certificate Of Occupancy or Temporary Certificate Of Occupancy must be obtained before the tenant space can be staffed, stocked or open to the general public. All required licenses shall be obtained prior to operation. If the Certificate Of Occupancy cannot be obtained before the business opens it is possible, with approval from all relevant City Departments, for the Building Official to issue a Temporary Certificate Of Occupancy after the Final inspection. The maximum length of time a business can operate on a Temporary Certificate of Occupancy is six (6) months and the certificate must be obtained from City Hall and a fee paid for at that time. Please contact the Codes Administration Division at 913-742-6010 to schedule a Final inspection or inquire about Occupancy.