Connect Shawnee



Project Description:

"Connect Shawnee" includes three trail connections as shown on the attached exhibit. Two of the connections will provide direct access to the Clear Creek Trail from the Grey Oaks subdivision and the Woodland Park subdivision. The third location will connect the sidewalk on 66th Street to Gum Springs Park. The connections will provide safe, convenient, and cost-effective transportation options to schools and parks.

City was awarded $458,500 in 2015 Kansas Transportation Alternatives (TAP) funds for the project.



Last Updated:
01/03/2017

Capital Improvement

Project Category:
Parks & Facilities

Project Contact:
Bert Schnettgoecke, P.E., (913)742-6271

Design Firm:
TranSystems

Construction Contract:
Pyramid Contractors, Inc.

Inspection Firm:
TranSystems

Project Status:
Construction

Project Number:
3412

Project Start Date:


Estimated Project End Date:


Status Details:

Project design started on November 10, 2015 and preliminary plans are complete.




Notices:

A neighborhood informational meeting was conducted on February 10, 2016 at the Shawnee Civic Centre (13817 Johnson Drive). The preliminary plans were presented at the meeting, and neighbors adjacent to the project sites provided comments and feedback to City Staff. The preliminary plans are attached below for review.

The City is continuing to acquire easements for this project but is still expected to finish on schedule. The next neighborhood informational meeting will be in May.

Plans - Final.pdfPlans - Final.pdf

Bids were received 9/28/16.

Pyramid Contractors was awarded the contract by City Council on 11/14/16.

A Pre-Construction Meeting was held with Pyramid Contractors, KDOT, TranSystems, and several Subcontractors on 12/16/16.