Johnson Drive & Mund Storm Drainage Improvements



Project Description:

The storm drainage system that runs across Johnson Drive at Mund Rd is in need of replacement. This entire system has been inspected and is in dire need of repair. The purpose of this project will be to remove and replace this underground pipe system from approximately the cul-de-sac of 55th Terrace & Brownridge north across Johnson Drive.



Last Updated:
06/21/2017

Capital Improvement

Project Category:
Drainage Improvements

Project Contact:
Paul Lindstrom, P.E. (913)742-6234

Design Firm:
GBA

Construction Contract:
Blue Nile Construction

Inspection Firm:
GBA

Project Status:
Construction

Project Number:
3426

Project Start Date:
06/26/2017

Estimated Project End Date:
08/25/2017


Status Details:

GBA has been working on the plans for construction of the improvements. A neighborhood meeting was held on March 8th, 2017. The final plans were approved at the March 27th, 2017 City Council. There will be a combination of pipe removal and replacement and slip-lining. The project bid on May 3rd, 2017 and was approved at the May 8, 2017 City Council meeting. Work to begin on June 26th.




Notices:

Johnson and Mund Kick-Off Meeting Survey Notice_09232016.pdfJohnson and Mund Kick-Off Meeting Survey Notice_09232016.pdf3429_Johnson_and_Mund_Final_Plans.pdf3429_Johnson_and_Mund_Final_Plans.pdf

Images: